Power loading of an installation: Difference between revisions
m (r2.7.2) (robot Adding: ru:Силовая нагрузка электроустановки) |
m (cleaned up source: table format, etc ...) |
||
Line 12: | Line 12: | ||
{| | {{Manual_TOC | | ||
* [[Installed power (kW)|Installed power (kW)]] | * [[Installed power (kW)|Installed power (kW)]] | ||
* [[Installed apparent power (kVA)|Installed apparent power (kVA)]] | * [[Installed apparent power (kVA)|Installed apparent power (kVA)]] | ||
Line 22: | Line 20: | ||
* [[Choice of transformer rating|Choice of transformer rating]] | * [[Choice of transformer rating|Choice of transformer rating]] | ||
* [[Choice of power-supply sources|Choice of power-supply sources]] | * [[Choice of power-supply sources|Choice of power-supply sources]] | ||
}} | |||
[[ru:Силовая нагрузка электроустановки]] | [[ru:Силовая нагрузка электроустановки]] |
Revision as of 13:10, 15 November 2013
In order to design an installation, the actual maximum load demand likely to be imposed on the power-supply system must be assessed.
To base the design simply on the arithmetic sum of all the loads existing in the installation would be extravagantly uneconomical, and bad engineering practice.
The aim of this chapter is to show how some factors taking into account the diversity (non simultaneous operation of all appliances of a given group) and utilization (e.g. an electric motor is not generally operated at its full-load capability, etc.) of all existing and projected loads can be assessed.
The values given are based on experience and on records taken from actual installations. In addition to providing basic installation-design data on individual circuits, the results will provide a global value for the installation, from which the requirements of a supply system (distribution network, MV/LV transformer, or generating set) can be specified.