Chapter G

Sizing and protection of conductors


Sizing of busbar trunking systems (busways): Difference between revisions

From Electrical Installation Guide
*>CleanUpAuto
(clean-up 2016 - imported revision step 20)
m (Text replacement - "\[\[ru:[^]]*\]\][ \r\n]*" to "")
 
(13 intermediate revisions by 3 users not shown)
Line 1: Line 1:
{{Menu_Sizing_and_protection_of_conductors}}  
{{Menu_Sizing_and_protection_of_conductors}}__TOC__
<br>
__TOC__
The selection of busbar trunking systems is very straightforward, using the data provided by the manufacturer. Methods of installation, insulation materials, correction factors for grouping are not relevant parameters for this technology making the selection of busways much more straightforward than the sizing of a traditional distribution with cables.  
The selection of busbar trunking systems is very straightforward, using the data provided by the manufacturer. Methods of installation, insulation materials, correction factors for grouping are not relevant parameters for this technology making the selection of busways much more straightforward than the sizing of a traditional distribution with cables.  


The cross section area of any given model has been determined by the manufacturer based on:  
The cross section area of any given model has been determined by the manufacturer based on:  
*The rated current,  
*The rated current,  
*An ambient air temperature equal to 35 °C,  
*An ambient air temperature equal to 35 °C,  
Line 12: Line 9:
=== Rated current  ===
=== Rated current  ===


The rated current can be calculated taking account of:  
The rated current can be calculated taking into account:  
 
*The layout,  
*The layout,  
*The current absorbed by the different loads connected along the trunking system.
*The current absorbed by the different loads connected along the trunking system.
Line 19: Line 15:
=== Ambient temperature  ===
=== Ambient temperature  ===


A correction factor has to be applied for temperature higher than 35 °C. The correction factor applicable is provided by the busway manufacturer. As an example, for Schneider Electric medium and high power range (up to 4000 A) the correction factor is given in {{FigureRef|G23a}}.<br>
A correction factor has to be applied for temperature higher than 35 °C. The correction factor applicable is provided by the busway manufacturer. As an example, for Schneider Electric medium and high power range (up to 4000 A) the correction factor is given in {{FigureRef|G24}}.
 


{{tb-start|id=Tab1196|num=G24|title=Correction factor for air temperature higher than 35 °C|cols=3}}
{| class="wikitable"
{| class="wikitable"
|-
|-
Line 39: Line 35:
|}
|}


'''''Fig. G23a:'''''<i>&nbsp;Correction factor for air temperature higher than 35 °C</i>
=== Neutral current  ===


Where 3<sup>rd</sup> harmonic currents are circulating, the neutral conductor may be carrying a significant current and the corresponding additional power losses must be taken into account.


=== Neutral current  ===
{{FigureRef|G25}} represents the maximum admissible phase and neutral currents (per unit) in a high power busbar trunking system as functions of 3<sup>rd</sup> harmonic level. For more information, see [[Harmonic currents in the selection of busbar trunking systems (busways)]].


Where 3<sup>rd</sup> harmonic currents are circulating, the neutral conductor may be carrying a significant current and the corresponding additional power losses must be taken into account.<br>{{FigureRef|G23b}} represents the maximum admissible phase and neutral currents (per unit) in a high power busbar trunking system as functions of 3<sup>rd</sup> harmonic level. For more information, see Chapter E - paragraph 2.3 "Harmonic currents in the selection of busbar trunking systems (busways)".
{{FigImage|DB422311_EN|svg|G25|Maximum admissible currents (p.u.) in a busbar trunking system as functions of the 3rd harmonic level}}


The layout of the trunking system depends on the position of the current consumers, the location of the power source and the possibilities for fixing the system.
* One single distribution line serves a 4 to 6 meter area
* Protection devices for current consumers are placed in tap-off units, connected directly to usage points.
* One single feeder supplies all current consumers of different powers.


[[File:FigG23b.jpg|500px|none]]
Once the trunking system layout is established, it is possible to calculate the absorbed current I<sub>n</sub> on the distribution line.
'''''Fig. G23b:'''''<i>&nbsp;Maximum admissible currents (p.u.) in a busbar trunking system as functions of the 3rd harmonic level.</i>  


I<sub>n</sub> is equal to the sum of absorbed currents by the current I<sub>n</sub> consumers: I<sub>n</sub> = Σ I<sub>B</sub>.


The layout of the trunking system depends on the position of the current consumers, the location of the power source and the possibilities for fixing the system.<br>&nbsp; - One single distribution line serves a 4 to 6 meter area<br>&nbsp; - Protection devices for current consumers are placed in tap-off units, connected directly to usage points.<br>&nbsp; - One single feeder supplies all current consumers of different powers.<br>Once the trunking system layout is established, it is possible to calculate the absorbed current I<sub>n</sub> on the distribution line.<br>I<sub>n</sub> is equal to the sum of absorbed currents by the current I<sub>n</sub> consumers: I<sub>n</sub> = Σ I<sub>B</sub>.<br>The current consumers do not all work at the same time and are not permanently on full load, so we have to use a clustering coefficient k<sub>S</sub>&nbsp;: In = Σ (I<sub>B</sub> . k<sub>S</sub>).  
The current consumers do not all work at the same time and are not permanently on full load, so we have to use a clustering coefficient k<sub>S</sub> : I<sub>n</sub> = Σ (I<sub>B</sub> . k<sub>S</sub>).  
 


{{tb-start|id=Tab1197|num=G26|title=Rated diversity factor according to the number of current consumers|cols=3}}
{| class="wikitable"
{| class="wikitable"
|-
|-
Line 64: Line 65:
| 1
| 1
|-
|-
| rowspan="5" | <br>Distribution (engineering workshop)  
| rowspan="5" | Distribution (engineering workshop)  
| 2...3  
| 2...3  
| 0.9
| 0.9
Line 80: Line 81:
| 0.5
| 0.5
|}
|}
 
{{tb-notes
Note: for industrial installations, remember to take account of upgrading of the machine equipment base. As for a switchboard, a 20&nbsp;% margin is recommended:<br>I<sub>n</sub> ≤ I<sub>B</sub> x k<sub>s</sub> x 1.2.<br>
|txn1= '''Note''': for industrial installations, remember to take into account the upgrading of the machine equipment base. As for a switchboard, a 20 % margin is recommended: I<sub>n</sub> ≤ I<sub>B</sub> x k<sub>s</sub> x 1.2}}
 
'''''Fig G24:'''''<i>&nbsp;Rated diversity factor according to the number of current consumers</i>
 
[[ru:Шинопроводы]]
[[zh:母线槽系统]]

Latest revision as of 09:48, 22 June 2022

The selection of busbar trunking systems is very straightforward, using the data provided by the manufacturer. Methods of installation, insulation materials, correction factors for grouping are not relevant parameters for this technology making the selection of busways much more straightforward than the sizing of a traditional distribution with cables.

The cross section area of any given model has been determined by the manufacturer based on:

  • The rated current,
  • An ambient air temperature equal to 35 °C,
  • 3 loaded conductors.

Rated current

The rated current can be calculated taking into account:

  • The layout,
  • The current absorbed by the different loads connected along the trunking system.

Ambient temperature

A correction factor has to be applied for temperature higher than 35 °C. The correction factor applicable is provided by the busway manufacturer. As an example, for Schneider Electric medium and high power range (up to 4000 A) the correction factor is given in Figure G24.

Fig. G24 – Correction factor for air temperature higher than 35 °C
°C 35 40 45 50 55
Correction factor 1 0.97 0.93 0.90 0.86

Neutral current

Where 3rd harmonic currents are circulating, the neutral conductor may be carrying a significant current and the corresponding additional power losses must be taken into account.

Figure G25 represents the maximum admissible phase and neutral currents (per unit) in a high power busbar trunking system as functions of 3rd harmonic level. For more information, see Harmonic currents in the selection of busbar trunking systems (busways).

Fig. G25 – Maximum admissible currents (p.u.) in a busbar trunking system as functions of the 3rd harmonic level

The layout of the trunking system depends on the position of the current consumers, the location of the power source and the possibilities for fixing the system.

  • One single distribution line serves a 4 to 6 meter area
  • Protection devices for current consumers are placed in tap-off units, connected directly to usage points.
  • One single feeder supplies all current consumers of different powers.

Once the trunking system layout is established, it is possible to calculate the absorbed current In on the distribution line.

In is equal to the sum of absorbed currents by the current In consumers: In = Σ IB.

The current consumers do not all work at the same time and are not permanently on full load, so we have to use a clustering coefficient kS : In = Σ (IB . kS).

Fig. G26 – Rated diversity factor according to the number of current consumers
Application Number of current consumers Ks Coefficient
Lighting, Heating 1
Distribution (engineering workshop) 2...3 0.9
4...5 0.8
6...9 0.7
10...40 0.6
40 and over 0.9 0.5
  • Note: for industrial installations, remember to take into account the upgrading of the machine equipment base. As for a switchboard, a 20 % margin is recommended: In ≤ IB x ks x 1.2