Choice of protection schemes with UPS: Difference between revisions

From Electrical Installation Guide
No edit summary
Line 5: Line 5:
The circuit-breakers have a major role in an installation but their importance often appears at the time of accidental events which are not frequent. The best sizing of UPS and the best choice of configuration can be compromised by a wrong choice of only one circuit-breaker.  
The circuit-breakers have a major role in an installation but their importance often appears at the time of accidental events which are not frequent. The best sizing of UPS and the best choice of configuration can be compromised by a wrong choice of only one circuit-breaker.  


===== Circuit-breaker selection  =====
== Circuit-breaker selection  ==


'''Figure N25''' shows how to select the circuit-breakers.  
'''Figure N25''' shows how to select the circuit-breakers.  
Line 11: Line 11:
----
----


<br>&nbsp;[[Image:FigN25.jpg|left|826x967px]]<br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br>'''''Fig. N25:'''''<i>&nbsp;Circuit-breakers are submitted to a variety of situations</i>  
<br>&nbsp;[[Image:FigN25.jpg|left|769x967px]]<br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br><br>'''''Fig. N25:'''''<i>&nbsp;Circuit-breakers are submitted to a variety of situations</i>  


----
----


===== '''Rating'''  =====
== '''Rating'''  ==


The selected rating (rated current) for the circuit-breaker must be the one just above the rated current of the protected downstream cable.  
The selected rating (rated current) for the circuit-breaker must be the one just above the rated current of the protected downstream cable.  


===== '''Breaking capacity'''  =====
== '''Breaking capacity'''  ==


The breaking capacity must be selected just above the short-circuit current that can occur at the point of installation.  
The breaking capacity must be selected just above the short-circuit current that can occur at the point of installation.  


===== '''Ir and Im thresholds'''  =====
== '''Ir and Im thresholds'''  ==


The table below indicates how to determine the Ir (overload; thermal or longtime) and Im (short-circuit; magnetic or short time) thresholds to ensure discrimination, depending on the upstream and downstream trip units.  
The table below indicates how to determine the Ir (overload; thermal or longtime) and Im (short-circuit; magnetic or short time) thresholds to ensure discrimination, depending on the upstream and downstream trip units.  
Line 63: Line 63:
----
----


===== Special case of generator short-circuits  =====
== Special case of generator short-circuits  ==


'''Figure N27 '''shows the reaction of a generator to a short-circuit.<br>To avoid any uncertainty concerning the type of excitation, we will trip at the first peak (3 to 5 In as per X”d) using the Im protection setting without a time delay.  
'''Figure N27 '''shows the reaction of a generator to a short-circuit.<br>To avoid any uncertainty concerning the type of excitation, we will trip at the first peak (3 to 5 In as per X”d) using the Im protection setting without a time delay.  

Revision as of 09:49, 16 June 2011


The circuit-breakers have a major role in an installation but their importance often appears at the time of accidental events which are not frequent. The best sizing of UPS and the best choice of configuration can be compromised by a wrong choice of only one circuit-breaker.

Circuit-breaker selection

Figure N25 shows how to select the circuit-breakers.



 

FigN25.jpg






















































Fig. N25: Circuit-breakers are submitted to a variety of situations


Rating

The selected rating (rated current) for the circuit-breaker must be the one just above the rated current of the protected downstream cable.

Breaking capacity

The breaking capacity must be selected just above the short-circuit current that can occur at the point of installation.

Ir and Im thresholds

The table below indicates how to determine the Ir (overload; thermal or longtime) and Im (short-circuit; magnetic or short time) thresholds to ensure discrimination, depending on the upstream and downstream trip units.

Remark (see Fig. N26)

  • Time discrimination must be implemented by qualified personnel because time delays before tripping increase the thermal stress (I2t) downstream (cables, semi-conductors, etc.). Caution is required if tripping of CB2 is delayed using the Im threshold time delay
  • Energy discrimination does not depend on the trip unit, only on the circuit-breaker


Type of downstream circuit Ir upstream /
Ir downstream ratio
Im upstream /
Im downstream ratio
Im upstream /
Im downstream ratio
Downstream trip unit All types Magnetic Electronic
Distribution > 1.6 > 2 > 1.5
Asynchronous motor > 3 > 2 > 1.5

Fig. N26: Ir and Im thresholds depending on the upstream and downstream trip units


Special case of generator short-circuits

Figure N27 shows the reaction of a generator to a short-circuit.
To avoid any uncertainty concerning the type of excitation, we will trip at the first peak (3 to 5 In as per X”d) using the Im protection setting without a time delay.



FigN27.jpg























Fig. N27: Generator during short-circuit