Functions of the substation with MV metering: Difference between revisions

From Electrical Installation Guide
m (Text replacement - "\[\[ru:[^]]*\]\][ \r\n]*" to "")
 
(14 intermediate revisions by 4 users not shown)
Line 1: Line 1:
{{Menu_Connection_to_the_MV_utility_distribution_network}}
{{Menu_Connection_to_the_MV_utility_distribution_network}}
== Connection to the MV network ==
Connection to the MV network can be made:
* By a single service cable or overhead line,
* By dual parallel feeders via two mechanically interlocked load-break switches
* Via a ring main unit including two load-break switches.


== MV/LV Transformers and internal MV distribution ==  
== MV/LV Transformers and internal MV distribution ==  
Line 10: Line 16:


* By simple radial feeders connected directly to the transformers or to the secondary substations
* By simple radial feeders connected directly to the transformers or to the secondary substations
* By one or several rings including the secondary MV/LV substations '''(Fig. B10)'''
* By one or several rings including the secondary MV/LV substations {{FigRef|B10}}
* By duplicate feeders supplying the secondary MV/LV substations.
* By duplicate feeders supplying the secondary MV/LV substations.


Line 18: Line 24:


It is not recommended to use MV/LV transformers above 2500 kVA due to:
It is not recommended to use MV/LV transformers above 2500 kVA due to:
* The high level of the short circuit current generated on the main LV switchboard.
* The high level of the short circuit current generated on the main LV switchboard.
* The number of LV cable required for the connection of the transformer to the LV switchboard.
* The number of LV cable required for the connection of the transformer to the LV switchboard.
Line 37: Line 42:


The generators can be connected:
The generators can be connected:
* At MV level to the MV main substation (see {{FigRef|B33}}).The generator(s) may be sized either for the supply of the whole installation or for a part only. In this case a load shedding system must be associated to the generator(s).
* At LV level on one or several LV switchboards requiring an emergency supply. At each location, the loads requiring an emergency supply may be grouped on a dedicated LV busbar supplied by a local generator (see {{FigRef|B31}} in [[Functions_of_a_substation_with_LV_metering#Local_emergency_generators|Local emergency generators at LV level]]).


* At MV level to the MV main substation (see '''Fig. B34)'''.The generator(s) may be sized either for the supply of the whole installation or for a part only. In this case a load shedding system must be associated to the generator(s).
{{FigImage|DB422035_EN|svg|B33|Connection of emergency generators at MV level}}
 
* At LV level on one or several LV switchboards requiring an emergency supply. At each location, the loads requiring an emergency supply may be grouped on a dedicated LV busbar supplied by a local generator (see '''Fig. B31)'''.
 
[[File:Fig_B34_2015.jpg|none|650px]]
'''''Fig. B34:''''' ''Connection of emergency generators at MV level''


== Capacitors ==
== Capacitors ==


Capacitors are intended to maintain the power factor of the installation at the contractual value specified by the utility. The capacitor banks can be fixed or adjustable by means of steps. They can be connected:
Capacitors are intended to maintain the power factor of the installation at the contractual value specified by the utility. The capacitor banks can be fixed or adjustable by means of steps. They can be connected:
* At MV level to the main MV substation
* At MV level to the main MV substation
* At LV level on LV switchboards.
* At LV level on LV switchboards.
Line 54: Line 55:
== LV main switchboard ==
== LV main switchboard ==


Every MV/LV transformer is connected to a main LV switchboard complying with the requirements listed for substation with LV metering (see 4.2.6).
Every MV/LV transformer is connected to a main LV switchboard complying with the same [[Functions_of_a_substation_with_LV_metering#LV_main_switchboard|requirements listed for substation with LV metering]].


== Simplified electrical network diagram ==
== Simplified electrical network diagram ==


The diagram '''(Fig. B35)''' shows:
The diagram {{FigRef|B34}} shows:
 
* The different methods to connect a MV/LV substation to the utility supply:
* The different methods to connect of a MV/LV substation to the utility supply:
**Spur network or single-line service
**Spur network or single-line service
**Single line service with provision for future connection to a ring or to dual parallel feeders
**Single line service with provision for future connection to a ring or to dual parallel feeders
Line 71: Line 71:


Compared with a substation with LV metering, a substation with MV metering includes in addition:
Compared with a substation with LV metering, a substation with MV metering includes in addition:
* A MV Circuit breaker functional unit for the general protection of the substation
* A MV Circuit breaker functional unit for the general protection of the substation
* A MV metering functional unit
* A MV metering functional unit
Line 82: Line 81:
The general protection usually includes protection against phase to phase and phase to earth faults. The settings must be coordinated with the protections installed on the feeder of the primary substation supplying the installation.
The general protection usually includes protection against phase to phase and phase to earth faults. The settings must be coordinated with the protections installed on the feeder of the primary substation supplying the installation.


 
{{FigImage|DB422036_EN|svg|B34|Consumer substation with MV metering}}
[[File:DB422036_EN.svg|none]]
'''''Fig. B35:''''' ''Consumer substation with MV metering''
 
[[ru:Функции подстанции с учетом на высоком напряжении]]
[[zh:中压计量变电站的作用]]

Latest revision as of 09:49, 22 June 2022

Connection to the MV network

Connection to the MV network can be made:

  • By a single service cable or overhead line,
  • By dual parallel feeders via two mechanically interlocked load-break switches
  • Via a ring main unit including two load-break switches.

MV/LV Transformers and internal MV distribution

As mentioned for substation with LV metering, only oil-immersed and dry type cast-resin transformers are allowed with the same rules of installation.

When the installation includes several MV/LV transformers and/or secondary MV/ LV substations an internal MV distribution network is required.

According to the required level of availability, the MV supplies to the transformers and the secondary substations may be made,

  • By simple radial feeders connected directly to the transformers or to the secondary substations
  • By one or several rings including the secondary MV/LV substations Fig. B10
  • By duplicate feeders supplying the secondary MV/LV substations.

For the two latter solutions the MV switchboard located in each secondary substation includes two load break switch functional units for the connection of the substation to the internal MV distribution and one transformer protection unit, for each transformer installed in the substation.

The level of availability can be increased by using two transformers operating in parallel or arranged in dual configuration with an automatic change over system.

It is not recommended to use MV/LV transformers above 2500 kVA due to:

  • The high level of the short circuit current generated on the main LV switchboard.
  • The number of LV cable required for the connection of the transformer to the LV switchboard.

Metering

The characteristics and the location of the VT’s and CT’s dedicated to the metering shall comply with the utility requirements.

The VT’s and CT’s are generally installed in the MV switchboard. A dedicated functional unit is in most of the cases required for the voltage transformers while the current transformers may be contained in the functional unit housing the circuit breaker ensuring the general protection of the substation.

The panel that contains the meters shall be accessible by the utility at any time.

Local emergency generators

Emergency standby generators are intended to maintain the power supply to the essential loads in the event of failure of the utility power supply.

According to the energy needs an installation may contains one or several emergency generators.

The generators can be connected:

  • At MV level to the MV main substation (see Fig. B33).The generator(s) may be sized either for the supply of the whole installation or for a part only. In this case a load shedding system must be associated to the generator(s).
  • At LV level on one or several LV switchboards requiring an emergency supply. At each location, the loads requiring an emergency supply may be grouped on a dedicated LV busbar supplied by a local generator (see Fig. B31 in Local emergency generators at LV level).
Fig. B33 – Connection of emergency generators at MV level

Capacitors

Capacitors are intended to maintain the power factor of the installation at the contractual value specified by the utility. The capacitor banks can be fixed or adjustable by means of steps. They can be connected:

  • At MV level to the main MV substation
  • At LV level on LV switchboards.

LV main switchboard

Every MV/LV transformer is connected to a main LV switchboard complying with the same requirements listed for substation with LV metering.

Simplified electrical network diagram

The diagram Fig. B34 shows:

  • The different methods to connect a MV/LV substation to the utility supply:
    • Spur network or single-line service
    • Single line service with provision for future connection to a ring or to dual parallel feeders
    • Dual parallel feeders
    • Loop or ring-main service
  • General protection at MV level
  • MV metering functions
  • Protection of MV circuits
  • LV distribution switchboard

Compared with a substation with LV metering, a substation with MV metering includes in addition:

  • A MV Circuit breaker functional unit for the general protection of the substation
  • A MV metering functional unit
  • MV Functional units dedicated to the connection and the protection of:
    • MV/LV transformers
    • MV feeders supplying secondary substations
    • MV capacitor banks
    • Emergency generators

The general protection usually includes protection against phase to phase and phase to earth faults. The settings must be coordinated with the protections installed on the feeder of the primary substation supplying the installation.

Fig. B34 – Consumer substation with MV metering
Share