Choice of architecture fundamentals: Difference between revisions
From Electrical Installation Guide
Migrate2019 (talk | contribs) (removed links to Chinese wiki) |
m (Text replacement - "\[\[ru:[^]]*\]\][ \r\n]*" to "") |
||
(One intermediate revision by the same user not shown) | |||
Line 10: | Line 10: | ||
{{Section-TOC}} | {{Section-TOC}} | ||
Latest revision as of 09:49, 22 June 2022
For the installations considered in this guide, the selection of an electrical architecture can be performed in two stages.
- The first stage is generally dedicated to:
- The selection of the mode of connection of the installation to the utility network,
- The choice of the internal MV distribution including:
- The definition of the number of MV/LV substations,
- The definition of the number of MV/LV transformers,
- The definition of the MV back-up generator when needed.
- The second stage deals with the principle of supply of the LV consumers