EMC implementation - Cabinet cabling

From Electrical Installation Guide
Revision as of 13:09, 28 January 2013 by WikiBot (talk | contribs) (r2.7.2) (robot Adding: zh:电磁兼容实施 - 机柜布线)

Home > ElectroMagnetic Compatibility (EMC) > EMC implementation > EMC implementation - Cabinet cabling

(Fig. R20)

Each cabinet must be equipped with an earthing bar or a ground reference metal sheet. All shielded cables and external protection circuits must be connected to this point. Anyone of the cabinet metal sheets or the DIN rail can be used as the ground reference.
Plastic cabinets are not recommended. In this case, the DIN rail must be used as ground reference.



Fig R20.jpg


















Fig. R20: The protected device must be connected to the surge-arrestor terminals


ru:Конструктивное исполнение ЭМС - разводка кабелей в шкафах zh:电磁兼容实施 - 机柜布线

Share