Choice of protection schemes with UPS: Difference between revisions
m (1 revision: no page modification, previous revision = imported ch.N pages cleaned-up) |
CleanUp2016 (talk | contribs) (Cleanup_2016) |
||
Line 1: | Line 1: | ||
{{Menu_Characteristics_of_particular_sources_and_loads}} | {{Menu_Characteristics_of_particular_sources_and_loads}} | ||
__TOC__ | __TOC__ | ||
Line 9: | Line 9: | ||
{{FigureRef|N25}} shows how to select the circuit-breakers. | {{FigureRef|N25}} shows how to select the circuit-breakers. | ||
{{FigImage|DB422660_EN|svg|N25|Circuit-breakers are submitted to a variety of situations}} | |||
== Rating == | == Rating == | ||
Line 24: | Line 23: | ||
The table below indicates how to determine the Ir (overload; thermal or longtime) and Im (short-circuit; magnetic or short time) thresholds to ensure discrimination, depending on the upstream and downstream trip units. | The table below indicates how to determine the Ir (overload; thermal or longtime) and Im (short-circuit; magnetic or short time) thresholds to ensure discrimination, depending on the upstream and downstream trip units. | ||
=== Remark === | |||
(see {{FigRef|N26}}) | |||
*Time discrimination must be implemented by qualified personnel because time delays before tripping increase the thermal stress (I<sup>2</sup>t) downstream (cables, semi-conductors, etc.). Caution is required if tripping of CB2 is delayed using the Im threshold time delay | *Time discrimination must be implemented by qualified personnel because time delays before tripping increase the thermal stress (I<sup>2</sup>t) downstream (cables, semi-conductors, etc.). Caution is required if tripping of CB2 is delayed using the Im threshold time delay | ||
*Energy discrimination does not depend on the trip unit, only on the circuit-breaker | *Energy discrimination does not depend on the trip unit, only on the circuit-breaker | ||
{| | {{TableStart|Tab1364|3col}} | ||
|- | |- | ||
! Type of downstream circuit | ! Type of downstream circuit | ||
! Ir upstream / | ! Ir upstream / | ||
! Im upstream / | Ir downstream ratio | ||
! Im upstream / | ! Im upstream / | ||
Im downstream ratio | |||
! Im upstream / | |||
Im downstream ratio | |||
|- | |- | ||
| Downstream trip unit | | Downstream trip unit | ||
Line 42: | Line 45: | ||
|- | |- | ||
| Distribution | | Distribution | ||
| | | > 1.6 | ||
| | | > 2 | ||
| | | > 1.5 | ||
|- | |- | ||
| Asynchronous motor | | Asynchronous motor | ||
| | | > 3 | ||
| | | > 2 | ||
| | | > 1.5 | ||
|} | |- | ||
{{TableEnd|Tab1364|N26|Ir and Im thresholds depending on the upstream and downstream trip units}} | |||
== Special case of generator short-circuits == | |||
{{FigureRef|N27}} shows the reaction of a generator to a short-circuit. | |||
To avoid any uncertainty concerning the type of excitation, we will trip at the first peak (3 to 5 In as per X”d) using the Im protection setting without a time delay. | |||
{{FigImage|DB422661_EN|svg|N27|Generator during short-circuit}} | |||
[[ru:Выбор схем защиты ИБП]] | [[ru:Выбор схем защиты ИБП]] | ||
[[zh:UPS保护方案的选择]] | [[zh:UPS保护方案的选择]] |
Revision as of 00:57, 9 December 2016
The circuit-breakers have a major role in an installation but their importance often appears at the time of accidental events which are not frequent. The best sizing of UPS and the best choice of configuration can be compromised by a wrong choice of only one circuit-breaker.
Circuit-breaker selection
Figure N25 shows how to select the circuit-breakers.
Rating
The selected rating (rated current) for the circuit-breaker must be the one just above the rated current of the protected downstream cable.
Breaking capacity
The breaking capacity must be selected just above the short-circuit current that can occur at the point of installation.
Ir and Im thresholds
The table below indicates how to determine the Ir (overload; thermal or longtime) and Im (short-circuit; magnetic or short time) thresholds to ensure discrimination, depending on the upstream and downstream trip units.
Remark
(see Fig. N26)
- Time discrimination must be implemented by qualified personnel because time delays before tripping increase the thermal stress (I2t) downstream (cables, semi-conductors, etc.). Caution is required if tripping of CB2 is delayed using the Im threshold time delay
- Energy discrimination does not depend on the trip unit, only on the circuit-breaker
Type of downstream circuit | Ir upstream /
Ir downstream ratio |
Im upstream /
Im downstream ratio |
Im upstream /
Im downstream ratio |
---|---|---|---|
Downstream trip unit | All types | Magnetic | Electronic |
Distribution | > 1.6 | > 2 | > 1.5 |
Asynchronous motor | > 3 | > 2 | > 1.5 |
Special case of generator short-circuits
Figure N27 shows the reaction of a generator to a short-circuit.
To avoid any uncertainty concerning the type of excitation, we will trip at the first peak (3 to 5 In as per X”d) using the Im protection setting without a time delay.