Number and localisation of MV/LV transformer substations: Difference between revisions
From Electrical Installation Guide
m (r2.7.2) (robot Adding: ru:Число и расстановка трансформаторных подстанций высокого/низкого напряжения) |
m (Text replacement - "\[\[ru:[^]]*\]\][ \r\n]*" to "") |
||
(11 intermediate revisions by 5 users not shown) | |||
Line 1: | Line 1: | ||
{{ | {{Menu_MV_and_LV_architecture_selection_guide}} | ||
The main criteria to consider for determination of the number and the location of the MV/LV substations are the following: | |||
* Number of buildings | |||
* Surface of each building | |||
* Number of floors per building | |||
* Repartition and power of the consumers | |||
* Power demand per area, floor, building | |||
* Sensitivity to interruption, need for redundancy | |||
To determine the number and the location of the MV/LV substations, we may however give the following basic indications: | |||
* Small and medium size building: One single MV/LV substation | |||
* Large building: One or several MV/LV substations depending on the power and the repartition of the consumers | |||
* Building with several floors: One or several MV/LV substations depending on the power and the repartition of the consumers. One MV/LV substation may be dedicated to each floor | |||
* Large site with several buildings: One MV/LV substation may be dedicated to each building. | |||
* | |||
* | |||
* | |||
Latest revision as of 09:48, 22 June 2022
The main criteria to consider for determination of the number and the location of the MV/LV substations are the following:
- Number of buildings
- Surface of each building
- Number of floors per building
- Repartition and power of the consumers
- Power demand per area, floor, building
- Sensitivity to interruption, need for redundancy
To determine the number and the location of the MV/LV substations, we may however give the following basic indications:
- Small and medium size building: One single MV/LV substation
- Large building: One or several MV/LV substations depending on the power and the repartition of the consumers
- Building with several floors: One or several MV/LV substations depending on the power and the repartition of the consumers. One MV/LV substation may be dedicated to each floor
- Large site with several buildings: One MV/LV substation may be dedicated to each building.