For the installations considered in this guide, the selection of an electrical architecture can be performed in two stages.
For the installations considered in this guide, the selection of an electrical architecture can be performed in two stages.
* The first stage is generally dedicated to:
* The first stage is generally dedicated to:
** The selection of the mode of connection of the installation to the utility network,
** The selection of the mode of connection of the installation to the utility network,
** The choice of the internal MV distribution including:
** The choice of the internal MV distribution including:
&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;- The definition of the number of MV/LV substations,<br>
***The definition of the number of MV/LV substations,
&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;- The definition of the number of MV/LV transformers,<br>
***The definition of the number of MV/LV transformers,
&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;- The definition of the MV back-up generator when needed.<br>
***The definition of the MV back-up generator when needed.
* The second stage deals with the principle of supply of the LV consumers  
* The second stage deals with the principle of supply of the LV consumers  


 
{{Section-TOC}}
{{Manual_TOC |
* [[Connection to the utility network]]
* [[Internal MV circuits]]
* [[Number and localisation of MV/LV transformer substations]]
* [[Number of MV/LV transformers]]
* [[MV back-up generator]]
}}
 
[[ru:Выбор основных элементов архитектуры]]
[[zh:系统基本条件的选择]]

Latest revision as of 09:49, 22 June 2022

For the installations considered in this guide, the selection of an electrical architecture can be performed in two stages.

  • The first stage is generally dedicated to:
    • The selection of the mode of connection of the installation to the utility network,
    • The choice of the internal MV distribution including:
      • The definition of the number of MV/LV substations,
      • The definition of the number of MV/LV transformers,
      • The definition of the MV back-up generator when needed.
  • The second stage deals with the principle of supply of the LV consumers