Configuration of LV circuits: Difference between revisions

From Electrical Installation Guide
m (r2.7.2) (robot Adding: zh:低压回路的配置)
Line 159: Line 159:


[[ru:Конфигурация цепей низкого напряжения]]
[[ru:Конфигурация цепей низкого напряжения]]
[[zh:低压回路的配置]]

Revision as of 10:58, 28 January 2013


Main possible configurations (see figures D18 to D25):

  • Radial single feeder configuration: This is the reference configuration and the most simple. A load is connected to only one single source. This configuration provides a minimum level of availability, since there is no redundancy in case of power source failure.


FigD18.jpg













Fig. D18: Radial single feeder configuration


  • Two-pole configuration: The power supply is provided by 2 transformers, connected to the same MV line. When the transformers are close, they are generally connected in parallel to the same MLVS.


FigD19.jpg














Fig. D19: Two-pole configuration


  • Variant: two-pole with two ½ MLVS: In order to increase the availability in case of failure of the busbars or authorize maintenance on one of the transformers, it is possible to split the MLVS into 2 parts, with a normally open link (NO). This configuration generally requires an Automatic Transfer Switch, (ATS).


FigD20.jpg














Fig. D20: Two-pole configuration with two ½ MLVS and NO link


  • Shedable switchboard (simple disconnectable attachment): A series of shedable circuits can be connected to a dedicated switchboard. The connection to the MLVS is interrupted when needed (overload, generator operation, etc)


FigD21.jpg
















Fig. D21: Shedable switchboard


  • Interconnected switchboards: If transformers are physically distant from one another, they may be connected by a bus
    bar trunking. A critical load can be supplied by one or other of the transformers. The availability of power is therefore improved, since the load can always be supplied in the case of failure of one of the sources.
    The redundancy can be:

    - Total: each transformer being capable of supplying all of the installation,
    - Partial: each transformer only being able to supply part of the installation. In this case, part of the loads must be disconnected 
      (load-shedding) in the case of one of the transformers failing.



FigD22.jpg
















Fig. D22: Interconnected switchboards


  • Ring configuration: This configuration can be considered as an extension of the configuration with interconnection between switchboards. Typically, 4 transformers connected to the same MV line, supply a ring using busbar trunking. A given load is then supplied power by several clustered transformers. This configuration is well suited to extended installations, with a high load density (in kVA/m²). If all of the loads can be supplied by 3 transformers, there is total redundancy in the case of failure of one of the transformers. In fact, each busbar can be fed power by one or other of its ends. Otherwise, downgraded operation must be considered (with partial load shedding). This configuration requires special design of the protection plan in order to ensure discrimination in all of the fault circumstances.


FigD23.jpg



























Fig. D23: Ring configuration


  • Double-ended power supply: This configuration is implemented in cases where maximum availability is required. The principle involves having 2 independent power sources, e.g.:

   - 2 transformers supplied by different MV lines,
   - 1 transformer and 1 generator,
   - 1 transformer and 1 UPS.
An automatic transfer switch (ATS) is used to avoid the sources being parallel connected. This configuration allows preventive and curative maintenance to be carried out on all of the electrical distribution system upstream without interrupting the power supply.



FigD24.jpg
















Fig. D24: Double-ended configuration with automatic transfer switch


  • Configuration combinations: An installation can be made up of several sub-asssemblies with different configurations, according to requirements for the availability of the different types of load. E.g.: generator unit and UPS, choice by sectors (some sectors supplied by cables and others by busbar trunking).


FigD25.jpg

















Fig. D25: Example of a configuration combination
1: Single feeder, 2: Switchboard interconnection, 3: Double-ended


For the different possible configurations, the most probable and usual set of characteristics is given in the following table:




 Characteristic to
 be considered
 Configuration
 Radial  Two-pole Sheddable load  Interconnected 
 switchboards
 Ring Double-ended
Site topology Any Any Any 1 level
5 to 25000m²
1 level
5 to 25000m²
Any
Location latitude Any Any Any  Medium or high Medium or high Any
Maintainability Minimal Standard Minimal  Standard Standard Enhanced
Power demand < 2500kVA Any Any  ≥ 1250kVA  > 2500kVA Any
Load distribution Localized loads Localized loads Localized load Intermediate or
uniform distribution
Uniform distribution Localized loads
Interruptions sensitivity Long interruption 
acceptable
Long interruption 
acceptable
Sheddable Long  interruption
acceptable
Long interruption
acceptable
Short or no 
interruption
Disturbances sensitivity Low sensitivity High sensitivity Low sensitivity High sensitivity High sensitivity High sensitivity
Other constraints / / / /  / Double-ended 
loads



ru:Конфигурация цепей низкого напряжения zh:低压回路的配置

Share